What the RFI Response Drafter actually produces

Turns a plain description of a field conflict into a formatted RFI with drawing references, distribution list, and a suggested resolution path, plus a matching follow-up email to push for a fast answer.

Real output from this tool's promptBeam vs. ductwork RFI at Gridline C4Generated 2026-08-29
The input
Project Name:
Riverside Medical Office Building
Rfi Subject:
Conflict between structural beam and mechanical ductwork at Gridline C4
Question:
Structural steel beam at gridline C4 conflicts with the 24x16 supply duct shown on mechanical drawings. Please advise whether to reroute ductwork, add a transfer duct, or revise beam depth.
Relevant Drawings:
S-302, M-401, A-501
Urgency:
High - blocking rough-in above ceiling in Zone B
Formatted RFI Document

REQUEST FOR INFORMATION (RFI)

================================================================ RFI No.: [RFI-047] Date Issued: [Insert Date] Project Name: Riverside Medical Office Building Project No.: [Insert Project Number] Project Address: [Insert Project Address] ================================================================

TO: [Architect of Record - Name/Firm] FROM: [General Contractor - Name/Firm] CC: [Owner's Representative]; [Structural Engineer of Record]; [Mechanical Engineer of Record]; [Project Superintendent]; [MEP Subcontractor]

DISTRIBUTION LIST:

  • [Owner - Name/Company]
  • [Architect - Name/Firm]
  • [Structural Engineer - Name/Firm]
  • [Mechanical Engineer - Name/Firm]
  • [General Contractor PM - Name/Firm]
  • [Mechanical Subcontractor - Name/Firm]
  • [Project File]
----------------------------------------------------------------
SUBJECT: Conflict Between Structural Beam and Mechanical Ductwork at Gridline C4
----------------------------------------------------------------

SPECIFICATION / DRAWING REFERENCE(S):

  • S-302 (Structural Framing Plan - Level 2)
  • M-401 (Mechanical Ductwork Plan - Level 2)
  • A-501 (Reflected Ceiling Plan / Building Sections)

PRIORITY / URGENCY: HIGH

REASON FOR URGENCY: This conflict is currently blocking above-ceiling rough-in activities in Zone B. Continued delay will impact the critical path schedule for MEP rough-in and subsequent ceiling grid installation.

REQUESTED RESPONSE DATE: [Insert Date - Recommend within 3 business days of issuance]

----------------------------------------------------------------

QUESTION / CLARIFICATION REQUESTED:

---------------------------------------------------------------- During coordination review and field verification of above-ceiling conditions in Zone B, a physical conflict has been identified at Gridline C4 between the structural steel beam shown on Drawing S-302 and the 24" x 16" supply air duct shown on Drawing M-401. The bottom flange of the structural beam intersects the required duct routing path at this location, leaving insufficient clearance for the ductwork to pass as currently designed.

Please review the attached field markup/photos (if applicable) and advise on the preferred resolution. Specifically, please confirm one of the following courses of action, or provide an alternative solution:

  • Reroute the 24"x16" supply duct around the beam (please advise on acceptable routing and any required duct size/shape transitions).
  • Approve installation of a transfer duct/sleeve through the beam web (please confirm if beam penetration is structurally permissible and provide any reinforcement requirements).
  • Revise the structural beam depth or configuration at Gridline C4 to accommodate the existing duct routing.

Contractor's Preliminary Recommendation (if any): [Insert GC's suggested solution, if applicable]

ATTACHMENTS:

[ ] Photos of Field Conditions [ ] Markup of S-302 [ ] Markup of M-401 [ ] Markup of A-501 [ ] Other: ___________________

----------------------------------------------------------------

SCHEDULE / COST IMPACT IF NOT RESOLVED:

---------------------------------------------------------------- Zone B above-ceiling rough-in (mechanical, electrical, plumbing, fire protection) cannot proceed until this conflict is resolved. Continued delay is projected to impact the overall project schedule by [Insert number] calendar days, with potential downstream effects on ceiling grid installation, insulation, and drywall trades in this zone. Additional costs may be incurred due to remobilization, standby labor, and schedule acceleration measures if not resolved promptly.

================================================================
RESPONSE (To be completed by Architect/Engineer):
================================================================

Response Provided By: ____________________________ Firm: ____________________________ Date of Response: ____________________________

Response: _________________________________________________________________ _________________________________________________________________ _________________________________________________________________ _________________________________________________________________

Impact Assessment (Cost/Schedule, if any): _________________________________________________________________ _________________________________________________________________

Attachments to Response: [ ] Revised Drawing(s) - Specify: ___________________ [ ] Sketch (SK) No.: ___________________ [ ] Other: ___________________

Signature: ____________________________ Date: ______________

================================================================
END OF RFI
================================================================
Follow-Up Email to Design Team

Subject: URGENT - Response Needed: RFI-047 (Structural/Duct Conflict at Gridline C4) - Riverside Medical Office Building

Dear [Architect/Engineer Name],

I hope this email finds you well. I am writing to follow up on RFI-047, formally submitted today, regarding a conflict between the structural steel beam and the 24"x16" supply ductwork at Gridline C4, as shown on Drawings S-302 and M-401.

This issue was identified during field verification of above-ceiling conditions in Zone B, and it is currently preventing our mechanical subcontractor from completing rough-in work in this area. Given the location of this conflict along a critical path for MEP rough-in, ceiling installation, and subsequent finish trades, we respectfully request an expedited review and response.

For your reference, we have asked for clarification on the following possible resolutions:

  • Rerouting the supply duct around the beam
  • Installing a transfer duct/sleeve through the beam web (pending structural approval)
  • Revising the beam depth or configuration at this location

Full details, drawing references, and supporting documentation are included in the attached RFI (RFI-047).

Due to the high priority of this issue, we kindly request a response no later than [Insert Requested Response Date - e.g., three business days from today]. Please let us know if a coordination call or site visit would help expedite a resolution - our team is available at your convenience.

Schedule Impact: If this RFI is not resolved by the requested date, we anticipate a delay of approximately [Insert Number] working days to the Zone B rough-in schedule, with downstream impacts to ceiling grid installation and subsequent finish work. We want to avoid any unnecessary schedule slippage and are happy to discuss options to mitigate impact while awaiting your direction.

Please do not hesitate to contact me directly at [Phone Number] or [Email Address] if you have any questions or need additional information to expedite your response.

Thank you for your prompt attention to this matter.

Best regards,

[Your Name] [Your Title] [Company Name] [Phone Number] [Email Address]

Attachment: RFI-047_Gridline-C4-Beam-Duct-Conflict.pdf

What to edit for your situation

Fill in the RFI number, project number/address, actual names/firms for the distribution list, and confirm the three proposed resolution options match what your super and MEP sub actually recommend before sending.

Human review: Have the structural and mechanical engineers of record verify the technical resolution before construction proceeds - this draft is a communication aid, not an engineering approval.